Project Description
Equipment Space Addition
Port St. Lucie, Florida
Client: Confidential
Construction Cost: $3.7 million
This project consisted of a 5,075 square foot addition of equipment space with a design for a future 2nd story. Also included was 510 square feet for an above ground Cable Vault and Utility area to relieve severe cable and AC ductwork congestion within the existing building. Chillers and four air conditioning units were replaced due to growth and age. A suspended ceiling was removed and major alterations were made to the ductwork and lighting to free up ceiling space for cabling.