Charlotte, NC | Confidential Client

Remove four existing 2,500KW generators and associated radiator, silencer, exhaust piping, electrical feeders, disconnect switches, control circuits, conduit, wiring, fuel oil connections & day tanks. Install three new generators 2,500KW and associated radiator, silencer, exhaust piping, electrical feeders, disconnect switches, control circuits, conduit, wiring, fuel oil connections & day tanks. Expand existing concrete inertia pads. Replace and expand existing exterior louvers and dampers at south generator room. Replace existing paralleling switchgear and controls. Replace existing fuel oil system controls and interior distribution piping. Modify existing CMU partition at north generator room to accommodate new equipment. Add new CRAC unit at switchgear room and related piping and ductwork. Remove and reroute existing ductwork and piping to accommodate new switchgear.